Projects
Göktepe WPP
Göktepe WPP
Yalova, Turkey
Capacity
112,7 MW
Service
Wind Power Plant
Customer
Polat Enerji
GOKTEPE WPP started operations in 2022 with 27 Enercon E-138, 4,2 MW wind turbines and an installed power of 112,7 MW.

Doguhan has provided Geological and Geophysical Soil Survey, Construction of Transportation and On- Site Roads, Crane, Turbine Foundations, Control Building and Switcyard. Apart from the 154 kV Substation installation, 3 line feeders were installed in 2 different energized substations and 2 different, totally 35 Km, 154 kV overhead lines turnkey works and 240 Km Mv Power Cables installation were completed in this project.